How the worked example scores 3 bidders
The template splits 100% between five criteria: technical/quality of proposal (25%), experience & track record (15%), methodology & work plan (15%), compliance & documentation (5%), and price (40%). Every non-price criterion is scored 0-5 by whoever is evaluating; price is scored automatically.
| Criteria | Weight | Bidder A | Bidder B | Bidder C |
|---|---|---|---|---|
| Technical / quality | 25% | 4 | 3 | 5 |
| Experience & track record | 15% | 3 | 2 | 4 |
| Methodology & work plan | 15% | 5 | 4 | 5 |
| Compliance & documentation | 5% | 4 | 3 | 5 |
| Price (bid ₹12.5L / ₹11.8L / ₹13.4L) | 40% | 4.72 | 5.00 | 4.40 |
| Total weighted score (out of 5) | 100% | 4.29 | 3.80 | 4.61 |
Bidder C wins here even though Bidder B quoted the lowest price, because quality and experience carry 60% of the weight. The price score rewards Bidder B for the lowest bid (full 5/5 on price) but that alone isn't enough to win on a quality-weighted tender.
The price formula
Price score = (lowest bid ÷ this bid) × maximum price score. The cheapest bid always scores full marks; every other bid scores proportionally less. This keeps price objective instead of a subjective 0-5 guess.
The rejection gate
A high weighted total should never save a bidder who fails a basic requirement. Apply a gate before comparing totals: for example, any bidder scoring below 3/5 on a non-price criterion, or a flat 0 on any criterion, is rejected outright — their total doesn't matter. The template flags this automatically per bidder.
For the full process — publishing criteria upfront, moderating scores across evaluators, and writing bidder feedback — see Tender Document Format and Bid Evaluation Template.
Frequently asked questions
What is a tender evaluation scoring matrix?
A table that scores every bidder against the same weighted criteria (such as technical quality, experience and price) on a common scale, usually 0-5, so bids can be compared objectively instead of on gut feel.
How is the price score calculated?
The most common method gives the lowest bid the full price score, and scores every other bid in proportion: price score = (lowest bid / this bid) x maximum price score. A bidder quoting the lowest price always gets full marks on price.
What is a rejection gate in tender evaluation?
A minimum-score rule applied before totals are compared — for example, any bidder scoring below 3 out of 5 on a mandatory criterion, or a 0 on any criterion, is rejected regardless of their overall weighted total.